| Ref | Project | Client | Value | Programme | Scope of Works | Status | Contact |
| 217 | Gatwick Pier 1 | Rokbuild Ltd | 134K | Apr 04-Nov 04 | Carpentry & Joinery Fit Out | Competed | |
| 226 | Heathrow T5 Baggage Accommodation | Mace | £839K | Oct 05-Nov 07 | Fit Out | Completed | Tonya Sanni - Project Manager; Adam Cartright - Quantity Surveyor |
| 235 | Heathrow T5 - CIP Lounge | Mace | £1.84M | Jan 07-May 08 | Doors, Frames, General Joinery and Fit Out | Completed | Andrew Butterworth - Package Manager; Simon Hoarsley - Project Manager;Anthony Sexton - Commercial Manager |
| 246 | Heathrow T3 - Transformation Room | Morgan Ashurst | £52K | Apr 08-Sep 08 | General Builderswork & Fit Out | Completed | Alan Smith - Project Manager; Neil Reynolds - Quantity Surveyor |
| 251 | Heathrow T3 - Virgin COGS | Morgan Ashurst | £80K | Nov 08-Jan 09 | General Builderswork | Completed | Rob Liddle - Project Manager; Richard Hawkins - Quantity Surveyor |